- In a brand-new building, install a large number of state-of-the-art crane/hoist and runway systems.
- These systems must offer superb flexibility in the handling of a diverse array of high-tech, high-value production parts.
- Complete the installation within 8 weeks.
This Virginia plant now has the “gold standard” in Crane Solutions.
Industry: Aerospace
Their Challenge:
Our Solution:
- Engineer an elaborate system of 24 two-ton crane-and-hoist systems and 10 runway systems.
- This turnkey installation includes bridge systems, hoist/trolley units, runway systems, a general column layout, radio controls with backups, and a telemotive laser anti-collision system.
- Assign a project manager with overall responsibility for the entire project.
- Coordinate the timely completion of all deliverables including engineering, procurement, and installation.
- Provide system warranties, training and manuals, and service support as needed.
The Results:
- The entire project was installed as scheduled and has been working flawlessly.
- The engineering, installation, and system training by Han-Tek have earned high praise from plant personnel.