Modernized 275-ton gantry crane on top of a hydroelectric dam during load testing with yellow water-filled test weights

Two 275-Ton Dam Cranes, Rebuilt Instead of Replaced

AC drives, radio controls and full code compliance brought two hydroelectric gantry cranes back to like-new operating condition.

2
gantry cranes modernized in place
The North and South cranes were rebuilt where they stand instead of being replaced.
5
motions converted from DC to AC drives
Main hoist, auxiliary hoist, bridge, trolley and gantry now run on Magnetek variable-frequency drives.
100%
of engineering-study deficiencies fixed
Every item in the independent Simmers Crane Design study was addressed on both cranes.
0
operators working at height to run the cranes
Cattron radio remotes let operators run both cranes from the dam deck.
The short version

A major Northeastern hydroelectric power authority relies on two 275-ton gantry cranes to raise and lower the dam's water control gates. After decades of service, both were out of code, worn, and running on DC drives that could no longer position gates precisely.

Han-Tek modernized both cranes in place instead of replacing them: AC drives on all five motions, radio remote control, new motors, gear reducers and brakes, structural repairs, and full OSHA, CMAA and NEC compliance.

01 The Challenge

Critical cranes that had fallen behind code

The two gantry cranes ride along the top of the dam and lift the gates that control water flow. Gate position decides how much water passes, so every move has to be precise and repeatable. After decades in service, neither crane could do that reliably.

01

Old DC drives

No smooth, variable-speed control, which made accurate gate positioning hard.

02

Out of code

Missing wind anemometers and rail clamps, unrated load markings, and gaps against OSHA, CMAA and NEC.

03

Worn and cracked

An engineering study found worn pins, drums, brakes and seals, plus cracked welds in the gantry legs.

Operators also had to climb up and run the cranes at dangerous heights on every cycle.

275-ton gantry crane positioned over the water control gates of a hydroelectric dam
One of the two gantry cranes over the dam's water control gates.
02 What Han-Tek Did

Modernize both cranes in place

Instead of replacing two 275-ton cranes, Han-Tek rebuilt both as single-point contractor, with P&H as the crane OEM partner for structural and mechanical work.

  • Drives: Magnetek VG+ AC drives on the main and auxiliary hoists and G+ drives on the bridge, trolley and gantry, replacing DC on all five motions.
  • Controls: Cattron Theimeg MP96 radio remotes, so operators run both cranes from the dam deck.
  • Components: new motors, SEW Eurodrive gear reducers, Hillmar/Mondel brakes, EMS festoon, Cutler-Hammer NEC-compliant panels and integrated load cells.
  • Code and safety: wind anemometers, rail clamps, rated load markings and cage modifications.
  • Mechanical and structural: redesigned truck saddle pins, drum and sheave repairs, new seals and hoist rope, and weld repairs found by non-destructive testing.
Rebuilt, not replaced

Both cranes were brought to like-new operating condition at a fraction of the cost and disruption of replacing them.

Running aging cranes that are out of code?

Tell us what you have and what it lifts. A Han-Tek engineer will tell you whether modernizing beats replacing.

03 The Results

Precise, code-compliant and safer to run

AreaBeforeAfter
Gate positioningDC drives, no smooth variable speedInfinitely variable on all five motions
Operator locationAt height on the craneDam deck, by radio remote
Code statusOut of OSHA, CMAA and NEC complianceFully compliant
Engineering study itemsOpen on both cranesAll addressed
  • Gate positioning restored: variable-frequency drives give precise, repeatable gate moves the old DC system could not.
  • No more work at height: operators run both cranes from the dam deck.
  • Full code compliance: both cranes now meet current OSHA, NEC and CMAA requirements.
  • Critical assets preserved: two 275-ton cranes back in like-new condition without the cost of replacement.
Yellow water-filled test weights hanging from a modernized gantry crane hook during load testing
Load testing with water-filled test weights before the cranes went back into service.
04 Common Questions

Questions about crane modernization

Is modernizing a crane better than replacing it?

Often, when the structure is sound. On this project both cranes were rebuilt in place to like-new operating condition at a fraction of the cost and disruption of replacement.

Can a DC crane be converted to AC drives?

Yes. All five motions on both cranes moved from DC to Magnetek AC variable-frequency drives, with new motors matched to the drives.

How do radio remotes improve crane safety?

Operators run the crane from a safe spot on the ground or deck, so nobody has to climb or ride the crane to operate it.

Which codes apply to gantry and overhead cranes?

OSHA, CMAA and NEC all set requirements. This project brought both cranes into compliance with all three.

Aging cranes?

Modernize or replace? Let's find out.

Send us the crane make, capacity and what it is doing today. A Han-Tek engineer will tell you what a modernization would take.

800.836.0237

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

Subscribe to Han-Tek Updates

Get new Han-Tek blog posts delivered to your inbox.

Prefer a feed reader?Follow Han-Tek by RSS →