Yellow single-girder overhead bridge cranes with festoon cable systems in a modern manufacturing facility Representative image

10 Crane Zones, One Turnkey System, One Month Early

Overhead cranes for every production, inspection and support area of a new jet engine component plant, released to production ahead of a fixed contract date.

10
crane zones in one turnkey system
Four production zones, three CMM inspection rooms, plus calibration, maintenance and stores.
8 wks
on-site install, no hit to the plant ramp-up
Installed while the rest of the new plant was being built out around it.
125%
load tested before turnover
A 2-ton crane is proven with 5,000 lb on the hook before anyone uses it, as OSHA requires.
1
Han-Tek project manager for every workstream
One person accountable for engineering, fabrication, install, testing, training and documents.
The short version

A Tier-1 aerospace manufacturer was opening a new plant for high-value rotating jet engine components. It needed overhead cranes in 10 separate zones, all ready by a fixed December 31 commissioning date.

Han-Tek engineered, built, installed, tested and documented every crane as one turnkey system under one project manager. The cranes were released to production on November 29, 32 days ahead of the contract date, and the customer came back for more crane work in later years.

01 The Challenge

Ten crane systems, one opening date

The plant needed lifting in every area where engine components are machined, measured and stored. Each zone had its own layout and its own runway, but all of them had to be running before the plant opened.

01

Ten different zones

Four production zones, three CMM inspection rooms, and dedicated cranes for calibration, maintenance and stores.

02

A date that could not move

Commissioning was fixed at December 31, and the install could not slow the rest of the plant ramp-up.

03

A secure site

An ITAR-controlled plant wanted one accountable supplier for engineering, install and turnover.

02 What Han-Tek Did

One supplier for every zone

  • Designed and built single-girder bridges in-house, each with an R&M 2-ton electric chain hoist.
  • Added Telemotive laser anti-collision on every bridge so cranes sharing a runway can't run into each other.
  • Used variable-frequency drive (VFD) bridge control for smooth starts and stops around high-value parts.
  • Delivered it turnkey: engineering, procurement, fabrication, about 8 weeks of install, OSHA-required 125% load testing, operator training and turnover documents.
  • Stocked a critical-spares package on site from the day the order was placed.
SYSTEM SPECS
Bridge speed120 fpm max, VFD control
Trolley speed80 / 20 fpm, two-speed
HoistR&M 2-ton electric chain, 16 fpm
Power460 V, 3-phase, 60 Hz
StandardCMAA Class C, indoor service
Every zone got its own runway and single-girder bridge. Production zones are outlined.
Planning a plant opening or crane expansion?

Send us your layout and your target date. A Han-Tek engineer will tell you what it takes to have every zone running on time.

03 The Results

Released a month ahead of the contract date

  1. Nov 29, 2010
    Released to production

    All crane systems handed over and running.

  2. Dec 3, 2010
    Final documentation delivered

    Manuals and turnover documents in the customer's hands.

  3. Dec 31, 2010
    Contract deadline

    The fixed commissioning date, beaten by 32 days.

  • Ahead of schedule: released to production 32 days before the contract date.
  • No disruption: the 8-week install ran on schedule without slowing the plant ramp-up.
  • Built to last: the systems remain in continuous service.
  • Repeat business: the customer came back to Han-Tek for more crane work at the same plant in later years.
04 Common Questions

Questions about multi-zone crane projects

Can one supplier handle cranes for an entire new plant?

Yes. On this project Han-Tek handled engineering, fabrication, install, load testing, training and documentation for all 10 zones under one project manager.

How do cranes on a shared runway avoid collisions?

Each bridge here has a Telemotive laser anti-collision system that slows and stops a crane before it reaches another one.

Does Han-Tek work in ITAR-controlled facilities?

Yes. This plant is ITAR-controlled, and Han-Tek engineered, installed and turned over the full crane system there.

Planning a new plant or expansion?

Need cranes in many areas by one date?

Send us your layout and your opening date. A Han-Tek engineer will tell you what it takes to get every zone running on time.

800.836.0237

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

Subscribe to Han-Tek Updates

Get new Han-Tek blog posts delivered to your inbox.

Prefer a feed reader?Follow Han-Tek by RSS →